| Technical Data |
 |
| Volume capacity per kg. |
52 in3 / 854 cc |
| Mixed density |
0.042 lbs per in3 /
1.17 gm per cc |
Coverage rate per kg.
@ 10-12 mils. |
30-35 ft2 / 3 m2 |
| Shelf life |
Indefinite |
| Volume solids |
100% |
| Mixing ratio |
Base |
Activator |
| By volume |
1.4 |
1 |
| By weight |
5.0 |
3 |
|

Cure Times |
 |
Ambient
Temperature |
Working
Life |
Touch
Dry |
Maximum
Overcoating |
Full
Cure |
| 41°F |
5°C |
50 min |
24 hrs |
30 hrs |
7 days |
| 59°F |
15°C |
40 min |
8 hrs |
24 hrs |
6 days |
| 77°F |
25°C |
30 min |
4 hrs |
24 hrs |
4 days |
| 86°F |
30°C |
25 min |
3 hrs |
24 hrs |
3 days |
|

Physical Properties |
 |
| |
Typical Values |
Test Method |
| Tensile Shear Adhesion |
| Steel |
2900 psi |
203 kg/cm2 |
ASTM D-1002 |
| Aluminum |
2400 psi |
168 kg/cm2 |
ASTM D-1002 |
| Copper |
2500 psi |
175 kg/cm2 |
ASTM D-1002 |
| Stainless steel |
2700 psi |
189 kg/cm2 |
ASTM D-1002 |
| Elcometer Adhesion to prepared cementitious surfaces primed with
ENECLAD™CFS is greater than the cohesive strength of the substrate. |
|

ENECLAD™CFS Technical Data |
 |
|
Theoretical coverage rate per kg. @ 3 mils. |
125 ft2 / 11.6
m2 |
|

|
| Mixing
Ratio |
Base |
Activator |
| By Volume |
2 |
1 |
| By Weight |
2.4 |
1 |
|

|
Ambient
Temperature |
Pot Life |
Minimum
Overcoating |
Maximum
Overcoating |
| 41°F |
5°C |
2 hrs |
3 days |
7 days |
| 59°F |
15°C |
40 min |
10 hrs |
36 hrs |
| 77°F |
25°C |
20 min |
5 hrs |
24 hrs |
| 86°F |
30°C |
15 min |
3 hrs |
16 hrs |
|
|
 |
 |
|

|
|
Surface Preparation - CHEMCLAD® XC should only be applied to clean, firm, dry, and well roughened surfaces. |
 |
1.Remove all loose material and surface contamination.

2.Depending on the surface, solvent clean and/or remove
contamination by abrasive blasting, steam cleaning, pressure
washing or other suitable means.

3. New concrete should be allowed to cure for a minimum of 28
days prior to treatment. Insure that all laitance is removed
from cementitious surfaces before applying CHEMCLAD®.

4. After removing all surface and sub-surface contamination,
flush the area as necessary and allow to dry completely.

5. Metallic surfaces which will be subject to immersion service
should be abrasive blasted to achieve a "white metal" finish and
a 3 mil profile. |
Priming Concrete Surfaces - Prior to applying CHEMCLAD XC
to concrete and/or cementitious substrates, the surface should
be treated with ENECLAD® CFS to seal the surface and insure
optimum adhesion is obtained. After mixing, CFS should be
applied using a brush or roller at the rate of 125 square feet
(11 - 12 square meters) per kilogram to achieve the recommended
film thickness of 3 mils.

Please note: Coverage
will be reduced on excessively rough and/or porous surfaces.
The application of the CHEMCLAD® XC may commence as
soon as the applied CFS is touch dry and should be completed
within 24 hours of Priming. For specific details concerning the
use of the CFS, please refer to the appropriate section of the
ENECLAD® CFS Tech Sheet.
Mixing & Application - CHEMCLAD XC is supplied in pre
-
measured quantities to simplify mixing of full units. Simply
pour
the contents of the Activator container into the Base container;
then, using a stirrer, or a paint mixer in an electric drill,
mix
thoroughly until a uniform, streak-free color is achieved. Apply
the mixed CHEMCLAD® XC to the prepared (and/or Primed)
surface using a brush, squeegee or roller. As a guide, a
coverage rate of 30 - 35 square feet (3 square meters) per
kilogram should result in an applied thickness of approximately
10 -12 mils on a relatively smooth surface. Please note: Shape,
contour, porosity, roughness, etc. will affect the coverage
obtainable. Since a minimum of two coats are recommended,
CHEMCLAD® XC is available in three colors, light gray dark
gray, and white to simplify over coating.

Health & Safety - Every effort is made to insure that
ENECON
products are as simple and safe to use as possible. Normal
industry standards and practices for housekeeping, cleanliness
and personal protection should be observed. For further
information and guidance, please refer to the detailed
MATERIAL SAFETY DATA SHEETS (MSDS) supplied with the
material and also available on request.

Cleaning Equipment - Wipe excess material from tools
immediately. Use acetone, MEK, isopropyl alcohol or similar
solvent as needed.

Technical Support - The ENECON engineering team is always
available to provide technical support and assistance. For
guidance on difficult application procedures or for answers to
simple questions, call your local ENECON® Fluid Flow Systems
Specialist or the ENECON® Engineering Center. |
|

All information contained herein is based on long-term testing in our laboratories as well as practical field experience and is believed to be reliable and accurate. No condition or warranty is given covering the results from use of our products in any particular case, whether the purpose is disclosed or not, and we cannot accept liability if the desired results are not obtained.
Copyright © 2008 by ENECON® Corporation. All rights reserved. No part of this work may be reproduced or used in any form or by any means - graphic, electronic or mechanical including photocopying, recording, taping or information storage and retrieval systems - without written permission of ENECON® Corporation.
|
|